Wiring the Components - Twelve Drummers

The most labour intensive part of the build was probably the wiring stage. Picture 6 shows the backplate with the equipment mounted on it, and in the very early stages of wiring up.

In total there were around 300 wires of different colours and sizes to cut to length, both ends stripped back, the ends “tinned”, then cable marker numbers put on, and finally the 600 ends secured into their respective termination points.

 

By now work was continuing 7 days a week, and the wiring was completed in just over a week (picture 7).

Picture 6 - Wiring in progress
Picture 7 – Wiring completed

Contributions by GordonG

TitleUpdatedType
Installing Onsite - Twelve Drummers 13 years 4 weeks agoBook page
Final Fitting - Twelve Drummers 13 years 4 weeks agoBook page
Wiring the Components - Twelve Drummers 13 years 4 weeks agoBook page
First Impressions - Twelve Drummers 13 years 4 weeks agoBook page
Backplate Assembly - Twelve Drummers 13 years 4 weeks agoBook page
Sourcing the Equipment - Twelve Drummers 13 years 4 weeks agoBook page
Unit Design - Twelve Drummers 13 years 4 weeks agoBook page
Design & Equipment - Twelve Drummers 13 years 4 weeks agoBook page
The Call to Arms! - Twelve Drummers 13 years 4 weeks agoBook page
Program Chart - Twelve Drummers 13 years 4 weeks agoBook page
Bringing the Display to Life - Twelve Drummers 13 years 4 weeks agoBook page
Programming the PLC - Twelve Drummers 13 years 4 weeks agoBook page

Book page

TitleCreated
240410 | Coroner to write to health secretary about ambulance delays prior to two deaths | called for improvements in response 2 days 15 hours agoBook page
240417 | Health campaigners fighting to see the return of 24-hour urgent care in West Cornwall say they now fear it may not happ 2 days 16 hours agoBook page
230417 | Hayle North Quay collapsed company Sennybridge leaves £135 million debts 4 days 4 hours agoBook page
240325 | Open letter to all party candidates | sign to help Cornwall Wildlife Trust make difference for Nature at election 3 weeks 2 days agoBook page
240310 | Detailed plans for affordable-led housing in Connor Downs 10th March 5 weeks 4 days agoBook page
240310 | Waste collections changes Helston, Penzance, Hayle | second phase:food waste, recycling, rubbish - commences July 5 weeks 4 days agoBook page
240224 | Doomed Hayle North Quay development through the years - in pictures 8 weeks 3 hours agoBook page
240218 | Collapsed North Quay development in Hayle described as a 'sea of despair' 8 weeks 2 days agoBook page
240214 | Hayle North Quay development collapse sees eight companies go bust Work has ground to a halt on the blocks of flats 8 weeks 4 days agoBook page
240220 | Poling works | Grist Lane and Marsh Lane, Angarrack | expected 20 Feb 2024 0830-1630, for one day 10 weeks 3 days agoBook page
231130 | Are you ready for weekly food waste recycling? | Food Waste, Recycling and Rubbish Collection Changes 19 weeks 1 day agoBook page
230821 | People of Cornwall town 'thrown under bus' over housing plan | direct result of councillors handled Hayle masterplan 34 weeks 2 days agoBook page